G702 Line-by-Line Explanation
Use this reference when you have a number in front of you and need to know where it belongs. The G702 summarizes the contract and the current payment request; its supporting detail comes from the continuation sheet.
Updated October 7, 2026 · PayAppPro editorial team
The nine lines, with one complete example
Assume a $100,000 original contract, a $10,000 approved addition, $60,000 completed and stored to date, $6,000 retainage, and $36,000 previously certified. There are no other adjustments in this example.
| Line | Meaning and source | Amount |
|---|---|---|
| 1 | Original contract sum: the executed agreement | $100,000 |
| 2 | Net approved change orders: additions less deductions | $10,000 |
| 3 | Contract sum to date: Line 1 + Line 2 | $110,000 |
| 4 | Total completed and stored to date: continuation-sheet total | $60,000 |
| 5 | Retainage currently held under the applicable rules | $6,000 |
| 6 | Total earned less retainage: Line 4 − Line 5 | $54,000 |
| 7 | Previous certificates for payment: prior certified total | $36,000 |
| 8 | Current payment due: Line 6 − Line 7 | $18,000 |
| 9 | Balance to finish, including retainage: Line 3 − Line 6 | $56,000 |
Read the labels as well as the amounts. Line 4 is cumulative; Line 8 is the new request for this application. Copying a cumulative amount into a current-period field can overstate the request even when the arithmetic looks tidy.
Why Line 9 is not the G703 balance
The uncompleted portion of this contract is $110,000 − $60,000 = $50,000. Another $6,000 has been earned but remains retained. Together they make the $56,000 on G702 Line 9.
G703 Column H shows scheduled value less completed and stored value. It does not add retained earnings back in. Therefore the total of Column H need not equal G702 Line 9 while retainage is held. The difference should be explainable by retainage, not hidden by changing a total.
Line 7 follows certification, not the bank balance
Suppose $36,000 was previously certified but only $30,000 has reached your bank. Line 7 still reflects the prior certified amount in this example. The unpaid $6,000 remains a collection/accounting issue; it is not new work to add to the next application.
Start from the last certified application and its approved adjustments. Do not silently substitute your invoice total, your original request, or cash received. If the reviewer reduced a prior request, reconcile the certified record before preparing the next one.
Check what Line 5 represents
With an unchanged 10% rate on all $60,000 earned, retainage is $6,000. A fixed-rate cumulative calculation can be correct. Separate work and stored-material rates, line-specific rates, reductions and releases require additional detail.
A retainage ledger is a useful reconciliation: opening held balance + new withholding − authorized releases = closing held balance. Compare that closing balance with Line 5. Do not apply a new rate to the entire job history unless the authorized treatment calls for it.
Form reference: AIA Contract Documents payment-application instructions. Check the edition and form required by your contract.
A short check before you sign
- Line 3 agrees with the approved contract and SOV.
- Line 4 agrees with the continuation-sheet completed-and-stored total.
- Line 5 agrees with the retainage calculation and any release record.
- Line 7 agrees with prior certification.
- Line 8 is 6 minus 7; Line 9 is 3 minus 6.
For project headings, signatures and submission order, use the G702 preparation instructions. This page is the numerical reference.
Frequently asked questions
Can Line 9 be positive when the work is complete?
Yes. If all work is earned but retainage remains held, Line 9 can equal that retained balance.
Is Line 8 the same as the increase in completed work?
Not necessarily. Retainage changes, stored materials and prior certification affect the amount due.
PayAppPro provides AIA-style outputs, not licensed AIA Contract Documents. AIA®, G702® and G703® are trademarks of the American Institute of Architects. Confirm the required form and billing rules in your contract. Numerical examples are illustrative, not customer records.