Skip to main content

Construction Progress Billing: A Three-Period Example

Progress billing lets you request payment as agreed work is earned instead of waiting for the entire project to finish. Each request needs to show both the progress to date and the part that has not already been certified.

Updated October 7, 2026 · PayAppPro editorial team

Agree on the billing basis first

A monthly cutoff tells you when to measure progress; it does not tell you how much has been earned. Start with the contract’s valuation method and approved breakdown. A lump-sum SOV, unit-price measurement and milestone schedule can support different evidence.

For an SOV-based job, assign value to identifiable work, agree on the structure, and use the same lines each period. Keep pending changes outside approved totals unless the governing procedure expressly permits different treatment.

Three periods on a $100,000 contract

Assume no changes, no stored materials and an unchanged 10% retainage rate. Each prior application is certified as requested. These are illustrative values, not a recommended retainage rate.

Cumulative values and the new request
MeasurePeriod 1Period 2Period 3
New work this period$20,000$30,000$25,000
Earned to date$20,000$50,000$75,000
Retainage held to date$2,000$5,000$7,500
Earned less retainage$18,000$45,000$67,500
Previously certified$0$18,000$45,000
Current payment request$18,000$27,000$22,500
Unearned contract balance$80,000$50,000$25,000

The $50,000 in Period 2 is not a second invoice for $50,000. After withholding and prior certification, the new request is $27,000. Across all three periods, requests total $67,500, which equals earned value less the $7,500 still retained.

Track certified amounts separately from cash received

If Period 1 is certified for $18,000 but remains unpaid when you prepare Period 2, keep its status in your receivables record. Do not reset the prior-certified amount to zero and request the same earnings again.

Maintain three separate columns in a billing log: requested, certified, and received. Record the submission date, certificate reference and payment date. That makes it possible to distinguish a disputed request from an approved payment that is simply overdue.

What changes when materials are stored?

Stored-material billing depends on permission and evidence. Once eligible materials have been counted in earned value, installing them does not earn their value a second time. Reduce the stored balance as that value enters completed work.

For example, moving $5,000 from storage to installed work with no other progress leaves total earned value unchanged. The two-period form example shows the actual columns. Keep new work, transfers and still-stored materials distinguishable.

A monthly routine the next person can follow

  1. Measure: collect progress through the agreed cutoff by SOV line.
  2. Reconcile: compare with the prior certified record and approved changes.
  3. Calculate: check cumulative earnings, retainage and the new request.
  4. Support: attach evidence for the amounts needing it.
  5. Close the loop: record reviewer adjustments, certification and later cash receipts separately.

The billing method and the document are different choices. Your contract may use AIA-style forms, a lender draw or an owner format. See the payment-application guide for assembling the submission.

Frequently asked questions

Is progress billing always monthly?

No. Billing intervals and milestones come from the contract. Use its cutoff and submission rules.

Does 100% complete mean all money is immediately due?

Not necessarily. Retainage, certification, closeout and other contract conditions can affect the remaining payment.

PayAppPro provides AIA-style outputs, not licensed AIA Contract Documents. AIA®, G702® and G703® are trademarks of the American Institute of Architects. Confirm the required form and billing rules in your contract. Numerical examples are illustrative, not customer records.