How to Fill Out AIA-Style G702 and G703
Start with the approved Schedule of Values and the last certified application. Update the continuation detail, reconcile the summary, then assemble the required backup. The example below shows the material transfer that often causes double counting.
Updated October 7, 2026 · PayAppPro editorial team
Gather five records before entering numbers
- The contract’s billing instructions and required form.
- The current approved SOV and authorized changes.
- The last certified application, including reviewer adjustments.
- Current progress and a record of materials still stored.
- Retainage terms and required attachments.
Use a consistent application number and period-ending date across the package. Establish the cutoff before collecting progress: a delivery after that date belongs in the next period unless the reviewer authorizes otherwise.
Complete the G703 before the G702
For standard G703 columns, carry prior completed work (D + E) into the new D. Do not put last period’s entire completed-and-stored total into D. Materials still stored remain in F; previously stored materials incorporated this period move into E and out of F.
| Column | Application 1 | Application 2 |
|---|---|---|
| C: Scheduled value | $50,000 | $50,000 |
| D: Previously completed work | $0 | $10,000 |
| E: Work this period | $10,000 | $13,000 |
| F: Materials presently stored | $15,000 | $10,000 |
| G: Completed and stored (D + E + F) | $25,000 | $33,000 |
| H: Balance to finish (C − G) | $25,000 | $17,000 |
In Application 2, $5,000 of the previously stored equipment is installed and $8,000 of additional work is performed. E is therefore $13,000; F falls by $5,000. Total earned value increases by only $8,000. The transfer is not a second charge for the same equipment.
Column reference: AIA G703–1992 instructions.
Transfer the totals to the G702
For this single-line example, assume 10% retainage on all earned value, no changes, no release, and Application 1 certified as requested.
| G702 line | Application 1 | Application 2 |
|---|---|---|
| 3: Contract sum | $50,000 | $50,000 |
| 4: Completed and stored | $25,000 | $33,000 |
| 5: Retainage | $2,500 | $3,300 |
| 6: Earned less retainage | $22,500 | $29,700 |
| 7: Previous certificates | $0 | $22,500 |
| 8: Current payment due | $22,500 | $7,200 |
| 9: Balance including retainage | $27,500 | $20,300 |
Application 2 asks for $7,200: the $8,000 increase less $800 additional retainage. It does not ask again for the $5,000 of material moved into installed work. If the first certificate was adjusted, reconcile those approved values rather than copying the original draft.
Form reference: AIA Contract Documents payment-application instructions. Check the edition and form required by your contract.
Reconcile before creating the final PDF
- SOV scheduled values equal the current approved contract sum.
- The continuation-sheet total agrees with G702 Line 4.
- Stored balances match the ledger and supporting records.
- Retainage agrees with the applicable rates and authorized releases.
- Line 7 agrees with prior certification, not bank deposits.
- Line 8 equals 6 − 7, and Line 9 equals 3 − 6.
Document a correction rather than making an unexplained change to prior history. For a single disputed line, identify the application and line number so the reviewer can follow the adjustment.
Finish the package and retain the accepted version
Attach the documents required for this request: perhaps stored-material evidence, signed changes, waivers or other project forms. Give each attachment a recognizable SOV or change-order reference. The supporting-document checklist includes examples.
Obtain the required signatures, submit through the specified channel, and save both the submitted and certified versions. The certified record—not an unapproved spreadsheet draft—is the starting point for the next billing cycle.
Frequently asked questions
Should previous work include last month’s stored materials?
For standard G703 Column D, carry prior D plus E. Materials that are still stored stay in F; material incorporated this period moves into E.
Can I use these numbers in PayAppPro directly?
These examples explain standard form outputs. Match each input to its label and the product’s workflow; a software input or ledger field may differ from a printed G703 column.
PayAppPro provides AIA-style outputs, not licensed AIA Contract Documents. AIA®, G702® and G703® are trademarks of the American Institute of Architects. Confirm the required form and billing rules in your contract. Numerical examples are illustrative, not customer records.