Skip to main content

Common G702 and G703 Errors: How to Find the Mismatch

When a number is wrong, identify the field and its source before changing the total. These examples are a numerical troubleshooting reference; use the separate submission checklist for the whole package.

Updated October 7, 2026 · PayAppPro editorial team

Error 1: billing a material transfer twice

Starting record: $10,000 completed and $15,000 stored. Next period, $5,000 of the stored material is installed and $8,000 of additional work is earned.

Wrong: carry $25,000 into previous work, add $13,000 current work and leave $10,000 stored. The resulting $48,000 counts prior stored value twice.

Correct standard G703 treatment: D = $10,000, E = $13,000 and F = $10,000. G = $33,000. The increase from $25,000 is $8,000. Reconcile the material ledger and check the two-period walkthrough.

Column reference: AIA G703–1992 instructions.

Error 2: replacing certificates with cash receipts

Starting record: prior certification is $36,000; cash received is $30,000; current earned less retainage is $54,000.

Wrong: deduct $30,000 and request $24,000 as the new application. Correct: deduct the $36,000 previously certified and request $18,000. Track the unpaid $6,000 separately. Confirm any authorized adjustments to the prior certificate before carrying it forward.

Error 3: making the two balances identical

With a $110,000 contract, $60,000 earned and $6,000 retained, G703 unearned balance totals $50,000. G702 Line 9 is $56,000 because it includes retainage.

Wrong: overwrite Line 9 to make it agree with the $50,000. Correct: use Line 3 minus Line 6 and explain the $6,000 difference. See the numbered-line reference.

Form reference: AIA Contract Documents payment-application instructions. Check the edition and form required by your contract.

Error 4: changing a rate without a release record

If $5,000 is held and the project authorizes a $2,000 release, the new held balance is $3,000 before any new withholding. It is not necessarily the result of applying a new rate to every historic dollar.

Check the scope and effective date of the authorization. Keep opening held balance, current withholding and release as separate entries. Reconcile the result with the summary and detailed support.

Error 5: adjusting only one side of a change

If an authorized $12,000 addition raises a $100,000 contract to $112,000, a $100,000 SOV no longer supports that summary. Conversely, a new $12,000 SOV line does not authorize a contract increase by itself.

Match the change identifier, signed amount and permitted billing treatment across the contract summary, SOV and supporting records. Keep unresolved scope identifiable instead of hiding it in an unrelated line.

Make the correction reviewable

List the affected application and field, the old value, the corrected value and the reason. Regenerate the dependent summary and detail together. A correction to stored materials can affect earnings, retainage and current due; changing just the final total leaves the package inconsistent.

For missing signatures, attachments and submission requirements, use the pre-submission checklist. For an application already returned, follow the resubmission workflow.

Frequently asked questions

Should I change prior certified values to make the new application balance?

Do not silently rewrite the accepted history. Reconcile the issue and record any authorized correction so the reviewer can follow it.

Does passing these checks guarantee approval?

No. Correct arithmetic does not establish scope entitlement, sufficient evidence or compliance with the submission requirements.

PayAppPro provides AIA-style outputs, not licensed AIA Contract Documents. AIA®, G702® and G703® are trademarks of the American Institute of Architects. Confirm the required form and billing rules in your contract. Numerical examples are illustrative, not customer records.