Confirm the project requirements
Use the contract, specifications and GC or owner checklist to confirm your scope and submission instructions.
Build your closeout package, one section at a time.
Work through the sections below as you organize your files. Check off what is done, skip what does not apply, and keep a printable record of what is left.
A cover and index, completion records, drawings, manuals, warranties, and required testing or training records. Final billing may be submitted separately.
Start with your contract and the GC or owner’s requirements. Use this list to organize them, then add anything specific to your job.
One project per browser. Download a backup before starting another; restore it later to resume your work.
Free CSV download includes all items and your notes. No signup needed.
Choose Done when you have completed the step, including any required review. Choose Not applicable after checking your scope. Add a note for anything still missing. The tool does not inspect or approve your documents.
25 items to review
Progress reflects your entries, not approval or payment eligibility.
Local saving becomes available when the tool loads. Entries stay on this device; avoid sensitive information on shared computers.
Backup and restore handle checklist entries only, on this device. Keep backups private.
Print and CSV include the whole checklist, even when sections are closed or items are hidden.
Confirm the instructions, identify the recipient, and make a list of the files you will send.
Use the contract, specifications and GC or owner checklist to confirm your scope and submission instructions.
Record the project, company, scope and the person receiving or reviewing the package.
Check naming and format instructions. Billing records may go to a different recipient.
List included filenames and revisions so the recipient can find each record.
Save exactly what you sent. When resubmitting, record which files changed.
Keep the date, recipient and email or portal confirmation. Receipt does not mean acceptance.
Record outstanding corrections in your notes. Mark done when the required review is finished.
Keep the evidence of completed work and any required sign-offs together.
Keep the required acceptance evidence for your scope; occupancy alone does not settle all closeout requirements.
Keep the final list and any required inspection or sign-off record together. Note who still needs to verify a correction.
Confirm which records belong to your scope and which the GC or owner supplies. Keep the approval reference or document location in your notes.
Include the drawings required for your scope in the requested formats.
Use the requested format and revision. Confirm that field changes are included and that the reviewer can open the files.
Use information for the equipment actually installed.
Use manuals for installed equipment, with model details, maintenance instructions and service contacts.
Make warranty coverage and the right service contact easy to find.
Check the project name, covered scope, contact details and required dates. Confirm the applicable start date rather than assuming it is the invoice date.
Collect the required reports and records of what was handed over.
Collect required test, commissioning and training records, including attendance or demonstration evidence.
List what was handed over, the quantity, recipient and date. Include only items required for your scope.
These records may go to accounting separately from the owner’s handover package.
Match the original contract plus net approved changes to the final Schedule of Values. List unresolved changes separately for follow-up; do not quietly bury them in a final total.
Confirm completed work, credits and any remaining balance. Resolve stored-material balances as materials are installed, returned or otherwise accounted for. Do not mark unfinished work complete just to close the spreadsheet.
Compare the last accepted application, previous certificates and the payment ledger. A late or partial payment does not automatically change the prior-certificate figure used on the next G702-style application.
Tie the continuation detail to the summary. Check application number, period, approved changes, retainage, signatures and any required notarization against the project instructions.
Compare the project total with prior applications, approved reductions and releases already billed. Keep retainage still held separate from unpaid amounts already requested.
Check the agreed release conditions and whether the reviewer wants a separate retainage application or a release within the final application. Document any amount that will remain held.
For a bonded project, confirm whether consent is required for final payment or a retainage reduction. Obtain the specified document from the surety rather than substituting a general release.
Confirm the correct form, amount, through-date and signing requirements with the reviewer. Conditional and unconditional releases have different effects; verify payment status and the applicable requirements before signing.
Check whether the contract requires evidence of coverage or other obligations continuing after final payment. Use the requested documents and dates.
Reconcile the receipt against amounts requested and retainage released. Keep accepted documents, payment records and any continuing warranty or correction obligations together.
Add any requirement from your contract or recipient’s checklist that is not covered above.
PayAppPro helps keep your Schedule of Values, prior billing, approved changes and retainage together while you prepare an AIA-style payment package.
Prepare your pay application See how billing worksUse these same sections to organize your files. This is a starting structure, not a universal submission standard. Your contract, scope and recipient’s instructions determine what belongs in the package.
For example, an HVAC subcontractor could put equipment manuals in section 4, warranties in section 5, and the controls training record in section 6. Keep the filenames in the index consistent with the actual files. Save a dated copy before sending a revision.
This structure draws on common closeout requirements illustrated by the University of Maryland’s O&M template and Harvard’s closeout documentation requirements. These are owner-specific references, not a certification standard for this checklist.
The tool tracks your checklist only. It does not upload documents or assemble your project files.
Suppose the accepted contract total is $100,000. All work is complete, previous certificates total $90,000, and $10,000 of retainage is now authorized for release. With no other adjustments and no retainage remaining, the final current request is $10,000.
If only $85,000 of those previous certificates has actually been paid, the total outstanding is $15,000: $5,000 from earlier certificates plus the new $10,000 request. Do not simply replace the $90,000 prior-certificate figure with cash received. Reconcile the overdue amount separately with the reviewer and your payment ledger.
For the line-by-line math, see G702 instructions and how retainage is calculated and billed.
Still sending monthly progress applications? Use the pay application supporting-documents checklist. For the final package, carry forward the accepted billing history, then work through the closeout requirements above. The lien-waiver guide explains the basic document types; confirm the actual form and requirements for your project.
Reference: AIA Contract Documents’ construction contract closeout guidance. This tool organizes your work; the contract and applicable requirements determine what must be delivered and accepted.
The package may include the final pay application, approved change-order reconciliation, retainage request, punch-list evidence, record drawings, O&M manuals, warranties, test or training records, and required waivers, affidavits or surety consent. The contract and requirements for your scope determine the actual list.
No. A project may be usable while punch-list work, documents or billing reviews remain open. Confirm the completion milestone and final-payment conditions for your project instead of treating occupancy as approval.
No. Start with the requirements for your subcontract and trade. Mark items Not applicable only after checking them, and add any GC-specific forms or documents that are missing.
Your entries save in this browser when local storage is available. They do not sync to a PayAppPro account or another device. Download a free CSV to work with the list in Excel, or use Print / save PDF to keep a copy. CSV files cannot be imported back into this tool. Use Download backup and Restore backup to resume an editable checklist on another browser. Restoring replaces the current checklist after confirmation. Clearing browser data can remove saved work.
No. It records the status you enter; it does not verify documents, approve a pay application or determine a payment due date. Keep the reviewer response and actual payment record alongside your checklist.